Oracle is discovering that building the future of enterprise computing is one thing—keeping the lights on for it is quite another. While the software giant rolls out artificial intelligence tools at a breakneck pace, its physical buildout is running into the kind of mundane obstacle that can derail even the most ambitious expansion plans: electricity.

At the turn of the month, Oracle unveiled Fusion Claw, a platform accompanied by 25 agent-based applications built on top of it. These programs run on Oracle Cloud Infrastructure and incorporate models from OpenAI and Gemini to automate business workflows. In a parallel move, the company expanded its compliance division with specialized software aimed at combating financial crime.

A Force Majeure Notice Casts a Shadow

Those software gains stand in sharp contrast to the complications emerging on the construction side. In late September, Oracle sent a force majeure notice to developer Stack Infrastructure, a subsidiary of Blue Owl, flagging possible delays in power supply for the Jupiter megaproject in New Mexico. According to Bloomberg, the facility is slated to come online in 2028.

The filing gives Oracle contractual cover to defer rent payments in the event of serious disruptions, though the company stressed that the project timeline remains unchanged. Blue Owl likewise emphasized that its financial obligations were unaltered, and Oracle told Reuters the initiative is still on schedule.

Even so, the episode has thrust the feasibility of Oracle's infrastructure ambitions into the spotlight. For market participants, the question is no longer whether the company can design cutting-edge software, but whether it can secure the power to run it. Shares changed hands at EUR 127.74 on the day, a modest gain of 1.0%.

Should investors sell immediately? Or is it worth buying Oracle?

The Balance-Sheet Question

The central issue for investors is whether Oracle can sustain its aggressive data-center spending without straining its finances. Media reports suggest the Jupiter notice amplified concerns about the liabilities the company has taken on for its data-center buildout. While Oracle has not cancelled its contractual payment obligations outright, resorting to legal protections exposes how vulnerable large-scale construction projects are to external infrastructure bottlenecks.

Financing the energy supply adds another layer of complexity. If utilities and partners cannot deliver grid capacity at the required pace, a gap opens between fixed costs already incurred and the revenue expected from new data centers.

A Founder's Signal

Against that uncertain operational picture, a move from the very top of the company stands out. On September 12, Larry Ellison scrapped his so-called 10b5-1 plan to sell company shares. No stock had been sold under the trading plan prior to its cancellation.

Such decisions carry weight on Wall Street. When a founder and major shareholder abandons a pre-arranged selling program entirely, the market typically reads it as an unambiguous vote of confidence. The implication is that Ellison views current valuations as too low for an exit—though whether that optimism is warranted depends on how quickly the newly restructured business segments deliver the hoped-for returns.

Restructuring Behind the Scenes

The apparent calm in the share price belies a tougher reality underneath. TechRadar reported on September 14 that layoffs were underway as part of a restructuring, affecting an unspecified number of employees. What makes the situation notable is the simultaneity: even as Oracle cuts staff in traditional areas, it continues hiring for artificial intelligence and data-center roles.

That pivot illustrates the immense pressure on management. Shrinking existing units to redirect billions into highly complex cloud and AI capacity is a risky wager. The stock has gained 8.4% over the past seven days, yet the transformation consumes enormous financial and human resources. Ultimately, the company is paying a price to avoid falling behind the major hyperscalers.

Partnerships and Product Rollouts

Oracle is not standing still on the partnership front. On September 28, it announced an integration with Swift's ledger network, designed to connect existing banking systems with tokenized deposit infrastructure. Days earlier, on September 24, Oracle Health revealed a collaboration with ID.me to digitize patient intake and eligibility verification.

On the stock market, Friday brought a 2.9% advance that closed the session at EUR 126.50. That gain, however, was not a homegrown success—it unfolded in the slipstream of a broadly firmer technology sector. Market reports pointed to a lack of company-specific catalysts behind the move.

Two Scenarios, One Stock

The optimistic case rests on Oracle quickly monetizing demand for its enterprise applications, thereby lifting utilization of existing infrastructure. If the new Fusion Claw features take hold seamlessly with major clients, the software division could generate steadier operating cash flows. Embedding leading AI models directly into established business processes gives the company a tangible point of differentiation.

Oracle at a turning point? This analysis reveals what investors need to know now.

Should large projects like Jupiter stay on track for 2028 despite the precautionary contractual steps, Oracle would lock in essential capacity ahead of competitors. In that scenario, the investments made would prove to be a strategic advantage once the next generation of agent-based enterprise software is fully operational.

The bearish case, by contrast, draws on mounting execution risks and potential margin pressure. If power-supply bottlenecks in New Mexico widen, Jupiter could slip behind its target timeline. Skepticism about profitability compounds the concern: an analysis by economists at Stanford University put the gap between AI spending and actual AI revenue at the leading hyperscalers at nearly one trillion dollars since 2024.

Technical Levels and Insider Exposure

On the corporate level, internal restructuring is adding to the unease. A filing with the U.S. Securities and Exchange Commission disclosed that Executive Chair Larry Ellison had pledged a total of 413,000,000 Oracle shares as collateral for personal obligations as of the September 21, 2026 reference date. Such concentration carries additional risk if market turbulence persists.

For the stock's near-term trajectory, much depends on how operational execution and chart technicals interact. As long as the shares defend their 50-day moving average of EUR 125.79, the technical foundation for a bottoming-out remains intact. Should investor confidence crack on further signs of project delays or rising financing burdens, the risks of the capital-intensive expansion are likely to regain the upper hand.

The next concrete checkpoint comes when Oracle hosts its AI World and SuiteWorld conferences from October 25 to 28, 2026. There, management will have to demonstrate just how far customer adoption of the new software solutions has actually progressed.

Ad

Oracle Stock: New Analysis - 5 October

Fresh Oracle information released. What's the impact for investors? Our latest independent report examines recent figures and market trends.

Read our updated Oracle analysis...

Disclaimer...

en | US68389X1054 | ORACLES | boerse | 70231243 |