First Phosphate's Quebec Blueprint: Bigger Ore Body, Same Unanswered Power Question
Published on 10/20/2026 at 16:41 | Editorial boerse-global.deFirst Phosphate is asking investors to look past a subdued share price and focus on what has changed underground. The Canadian project developer, which is working to build a North American supply chain for lithium iron phosphate (LFP) batteries, has seen its indicated resources at the Bégin-Lamarche deposit swell by 378%, a jump that Noble Capital analysts say puts the mine plan on firmer footing ahead of the looming feasibility study.
The market, at least in the immediate term, shrugged. The stock shed 5.0% in the previous session to close at 1.07 euros. By Tuesday it had edged back to 1.09 euros, a gain of 1.9%. Since the start of the year the shares are still up 52% to 55%, a range that reflects how much of the valuation rests on the company's ability to keep defining and de-risking its deposits in Quebec.
A Resource Upgrade That Matters for the Next Hurdle
The 378% increase in indicated resources is more than a headline number. For a mining project, the feasibility study is the threshold at which a geological prospect becomes a candidate for an economically viable operation, and a larger, better-defined resource base strengthens the case that Bégin-Lamarche can clear it. Management has not moved its target: the feasibility study is due in the first quarter of 2027.
That timeline sits inside a broader sequence that CEO John Passalacqua laid out at the Precious Metals & Critical Minerals virtual investor conference on 13 October. Environmental work is set to continue into the second quarter of 2027, a final investment decision is targeted for mid-2028, and production is envisioned around 2030. The company's plans cover both the extraction of phosphate in Quebec and its processing into battery-grade material — a two-stage ambition that adds complexity to every step.
Should investors sell immediately? Or is it worth buying First Phosphate?
The Money Is Lined Up, the Power Is Not
On the financial side, First Phosphate has assembled a substantial war chest. Management last reported liquid funds of 25 million CAD, supplemented by 21.5 million CAD in non-repayable government support and a further 22 million CAD available through state facilities. That combination is intended to carry the industrial infrastructure preparations forward.
What it cannot buy is a signature. According to regional outlet Le Réveil, the company is still waiting for confirmation of a power allocation for its planned phosphoric acid processing plant at the port of Saguenay. Without secured energy capacity, the operation cannot run on site — a bottleneck that illustrates how much of the project's fate lies with regulators and external framework conditions rather than with the company's own balance sheet.
A Long Runway With Familiar Risks
The gap between today's resource statement and first ore in roughly 2030 leaves investors exposed to years of permitting reviews, technical checks and final financing decisions. A mine start date of 2029 has also been cited by company representatives, including Alexis de la Renaudière, underscoring that the schedule remains a moving target.
Still, the strategic appeal of an independent North American battery supply chain has kept the stock well above its starting point for the year. Noble Capital's read is that the resource growth gives First Phosphate a sturdier platform for the feasibility work ahead. Whether that platform holds will depend on permits, power and the passage of time — three variables the company does not control.