- Taweelah C reached financial close on November 23, 2026, with a total project value of AED 7.76 billion.
- The 2.6 GW Abu Dhabi plant is designed to provide flexible generation and support renewable power integration.
- Commercial operations are forecast to begin in 2029.
Sembcorp Industries and its partners reached financial close on November 23, 2026, for the AED 7.76 billion Taweelah C independent power plant in Abu Dhabi. The milestone was announced by Sembcorp, TAQA, EWEC and Aljomaih Energy and Water Company.
The 2.6 GW plant is being developed under Abu Dhabi's independent power producer programme. It is designed to deliver flexible, high-efficiency gas-fired generation, strengthen grid stability and support the integration of larger volumes of renewable power.
Financing supports Abu Dhabi power expansion
TAQA owns 60 percent of the project company, while the consortium comprising Aljomaih Energy and Water Company and Sembcorp owns the remaining 40 percent. The partners are responsible for the facility's design, financing, construction, operation and maintenance.
The project is primarily funded through senior debt from local and international banks. China Energy Engineering Corporation has received the engineering, procurement and construction contract, while EWEC will purchase the plant's net electrical energy under the power purchase agreement.
Sembcorp stock traded at 4.03 euros on Lang & Schwarz at 20:37:16 CET on Tuesday, November 24, 2026.
Operations scheduled for 2029
Taweelah C is forecast to begin commercial operations in 2029. The project is intended to meet rising electricity demand linked to urbanisation, population growth and expanding data-centre activity while supporting Abu Dhabi's renewable-energy buildout.
Sembcorp Industries at a glance
- Company: Sembcorp Industries
- ISIN: SG1R50925390
- Project: Taweelah C independent power plant
- Project capacity: 2.6 GW
- Total project value: AED 7.76 billion
- Commercial operations: Forecast for 2029
- Lang & Schwarz quote: 4.03 euros on November 24, 2026, at 20:37:16 CET